Cypress Bridge Wellfield Improvements

The Cypress Bridge Wellfield, located in south-central Pasco and north-central Hillsborough counties, includes 10 production wells supplying an average of 11 million gallons of water per day (mgd) of drinking water up to a maximum of 40 mgd. The Cypress Bridge Wellfield began production with one well in 1988 and was expanded to 10 wells in 1996.

Overview

The project will replace pumps, motors, fans, louvers and electrical equipment at all 10 wells and replaces diesel generators at three wells.

Benefits

The Cypress Bridge Wellfield Improvements Project will improve reliability and safety by replacing infrastructure that has reached the end of its useful life and improve standby power and connectivity, and electrical safety.

Cost

Total cost for design and construction is $5,878,100.

Time Frame

Completion June 2024.

Public Impacts

This project has no public impact as all work is contained within Tampa Bay Water property.