Tampa Bypass Canal Pumps 

The Tampa Bypass Canal Pump Station, located in Hillsborough County, has the capacity to skim up to 200 million gallons of water per day from the Tampa Bypass Canal for treatment and immediate use at the Tampa Bay Regional Surface Water Plant in Brandon or storage in the C.W. Bill Young Regional Reservoir.

Overview

This project involves removing, inspecting and reconditioning the pumps and motors of eight vertical turbine raw water pumps. 

Benefits

This project will improve the reliability and efficiency of the pump station to support the agency’s surface water system.

Cost

The total budget for design and construction is $1.9 million.  

Time Frame

Construction is anticipated to begin in early 2027 and be completed by late 2030. 

Public Impacts

This project has no public impact as all work is contained within Tampa Bay Water property.