Surface Water Treatment Plant Expansion, left, and South Hillsborough Pipeline, right
20Nov
Regional Drinking Water Projects Make Progress
Construction, | | Return

Surface Water Treatment Plant Expansion  

The Surface Water Treatment Plant Expansion will add up to 12.5 million gallons per day of treatment capacity to help meet the region’s projected 2028 water needs. The project adds a fifth treatment train and the supporting systems needed to deliver that capacity. 

Construction is active in several areas across the plant. The contractor completed the 48-inch filter inlet piping, the drain piping and concrete encasement in the ozone train 5 area. The base slab for ozone contactor train 5 is also poured, and crews are now placing formwork and reinforcing steel for the ozone train 5 building. 

Belt filter presses 5, 6, and 7 are set in place, and utility connections and the new conduit duct bank are underway. The recycle-return water line is installed for filters 16 through 18. At the dry chemical building, the equipment foundations are complete and the new lime silo is in place.  

The project remains on schedule. Construction is about 17% complete, with expenditures at 30% of the $167 million budget. That spending reflects early procurement and construction activities and is consistent with expectations at this stage. 

South Hillsborough Pipeline 

The 26-mile-long South Hillsborough Pipeline will connect the expanded Surface Water Treatment Plant to the regional distribution system, delivering up to 65 million gallons of water per day to the Lithia and Balm areas when complete.  

Seven of the project’s 17 tunnel crossings are complete, and eight more are active. Segment A has five trenchless crossings underway and three open-cut crews working along North Moon Avenue, Ronele Drive and Boyette Road. Segment B has three trenchless crews building microtunnel shafts and an open-cut crew on Balm Boyette Road. 

Two major road closures begin in November. John Moore Road and Ronele Drive closed Nov. 12, and South Kings Avenue, south of Bloomingdale, closes Nov. 30. The project team is working with Hillsborough County Public Schools on bus rerouting and stop relocations, with coordinated messaging to families. 

Construction is about 16% complete, with expenditures at 30% of the $461.2 million construction budget. The project continues to progress as planned. To stay in the loop on project updates, sign up for email alerts here.