Milestone |
| December 2003 |
|
Feasibility analysis began |
| June 2004 |
Board approved project for implementation |
| November 2004 |
Pipeline route alternatives |
| November 9, 2004 |
Public Meeting - Open House |
| December 2004 |
Board selection of preferred route |
| March 2006 |
Complete design & permitting |
| March 17-May 2007 |
Trail to reopen. Pipe laying will continue along route to Anclote River (Area 5).
Temporary closures of paved trail due to deliveries of heavy equipment and pipe, likely for a few hours for a couple of weekdays each week.
Construction Staging Area (Area 3) will remain active. |
| May - September 2007 |
Construction from Anclote River (Area 5) to southern end of route (Area 6). No deliveries of heavy equipment or pipe; some minor activities, like wetland restoration, will continue. Construction Staging Area (Area 3) to remain active. |
| September - October 2007 |
New pipeline to be tested and cleaned. Water used to flush pipeline will be discharged near Area 3. |
| October - November 2007 |
New pipeline will be tied into an existing pipeline at western end of project. All facilities at front of Park, except the Education Center, will be closed (Area 1). |
| November - December 2007 |
Park to reopen while cleanup and closeout activities continue. |
| January 1, 2008 |
Complete project |