| Date |
|
Milestone |
| Spring 2001 |
|
Permitting complete |
| August 2001 |
Constuction began |
| November 2002 |
Obtained final operating permits |
| March 2003 |
Initial plant start-up |
| May 2003 |
Ran first acceptance test |
| February 19, 2004 |
Plant placed in standby mode |
| March 2004 |
Tampa Bay Water Seeks proposals from qualified teams to revamp the plant and operate it long-term. |
| November 2004 |
Tampa Bay Water Board of Directors approves agreements with American Water-Pridesa to resolve design and construction deficiencies |
| January 31, 2005 |
Large-scale pilot testing begins |
| June 2005 |
NPDES minor permit modification application submitted |
| September 2005 |
Complete design of remedied plant |
| October 2005 |
Commence construction |
| Spring 2007 |
Completed construction |
| End of 2007 |
Commence full operations |
|
|
 |
|