Public Input

Tampa Bay Water provides multiple opportunities for the public to provide comment on its projects. In April 2001, an initial public meeting introduced the project and informed the public about early feasibility studies. Three additional public hearings before the Tampa Bay Water board were held in Hillsborough, Pasco and Pinellas.

Residents in the areas near the alternative pipeline routes were asked for input on the routes in the summer of 2002. Additional open house meetings are planned for 2003, where additional public input on the project will be taken. The meeting will be publicly noticed.

Date   Milestone
1st Quarter 2002   Design and permitting work began
2nd-4th Quarter 2002 Pipeline routes feasibility study conducted
Public input taken
1st-4th Quarter 2003 Completed preliminary design
Obtained additional public input
1st-4th Quarter 2004 Complete design, permitting and property acquisition work
4th Quarter 2004 Begin Construction
December 2005 Project online and available to produce water to meet emergency needs

  
Contact Information

For more information or to be added to the mailing list, please contact Mike Coates, Tampa Bay Water project manager at (727) 796-2355.