Current Project Schedule, Phase II 

Date   Milestone
March 30, 2004   Tampa Bay Water closed on purchase of wells and Hillsborough County acquired the former FGUA service area
March 2005 Completed design and permitting activities
February 2006  Awarded construction
May 2006  Begin construction
January 2007  Complete construction

Construction Considerations

Tampa Bay Water recognizes that construction can be frustrating, particularly in densely populated neighborhoods.  Through careful planning and consideration of the surroundings, the agency will work to minimize inconvenience during construction projects by:

  • Notifying property owners in advance, when possible, if constuction activities might infringe upon residents (e.g. blocked driveways or sidewalks).
  • Working with city and county staff on plans to maintain traffic flow and to help residents navigate during construction.
  • Working to minimize dust during working hours.
  • Filling in all excavations and re-opening all lanes of traffic at the end of each work day.
  • Keeping citizens informed through direct mail, door hangers, web-site construction updates and communications with the homeowners association.