Project Schedule
| Date |
|
Milestone |
| August 2001 |
|
Permits Completed
Project Design Completed |
| October 2001 |
Property Acquisition Completed |
| July 2002 |
Construction Contract Awarded |
| July 2003 |
Original Contractor Abandoned Job |
| October 2003 |
Construction Resumed with Replacement Contractor |
| July 2004 |
Pipeline Placed into Service |
|
|
 |
|